Measure R: Process and Milestones
Timeline:
- Summer 2002 - Educational Master Plan Update completed.
- Spring 2003 - Facilities Master Plan Update completed.
- Summer 2003 - Initial project list and cost estimates developed for potential 2004 local bond measure from Facilities Master Plan.
- October 2003 - Proposed project list and cost estimates revised by administration.
- October 2003 - Information meetings conducted for all district staff. Anonymous poll results in 96% of district staff supporting proposed bond.
- November 2003 - Project list approved by Board of Trustees.
- December 2003 - Project list distributed to campus groups.
- Spring 2004 - Completed RFP/RFQ selection process for professional consultants.
- June 2004 - Five Year Construction Plan and FPP’s for Theater and Health & Sciences Building approved by Board of Trustees and submitted to state.
- June 2004 - Approved project list submitted to bond counsel.
- August 2004 - Bond measure text submitted for election.
- November 2004 - Measure R local bond APPROVED; 69% of voters approve bond.
- Fall 2004 - Construction project priorities and sequencing reviewed and approved by Board of Trustees and Administration.
- January 2005 - Theater Arts Facility project approved and funded by state. Administration approves start of project design.
- June 2005 - Five Year Construction Plan and FPP for Health & Sciences Building approved by Board of Trustees and submitted to state.
- Summer 2005 - Administration approves design start for following projects:
-
- Campus Infrastructure; IT Infrastructure; Agriculture Labs & Greenhouses; Facilities/Warehouse Facility; ADA/Safety Upgrades; Campus Parking Expansion; Physical Education Fields; Stadium Renovation; Auto Body Facility; Central Plant Expansion
-
- January 2006 - Health & Sciences Building project approved and funded by state. Administration approves start of project design. (As of 2014, last state capital outlay project funded)
- August 2006 - North Campus Parking Lots completed. First Measure R project completed.
- December 2008 - IT Infrastructure project completed.
- May 2009 - Facilities Services & Warehouse project completed.
- August 2009 - Agriculture Labs & Greenhouses project completed.
- August 2009 - Physical Education Fields & Marauder Stadium completed.
- August 2009 - West Parking Lots (#1, #2, #3) completed.
- February 2010 - Auto Body Facility project completed.
- August 2011 - Theater Arts Facility project completed.
- August 2011 - Parking Lot #5 project completed.
- August 2012 - Health & Sciences Building project completed.
- August 2012 - South Campus Renovation project completed.
- December 2013 - Campus Infrastructure project completed.
- March 2014 - Measure R fund balance reconciled. Final project list approved for design and construction.
- May 2014 - Measure R fund balance adjusted by Accounting for 13-14 expenses. Programming and planning initiated for remaining projects.